Archive for the ‘Industrial Construction’ Category

Mahle Warehouse- Leeds Park International

Thursday, June 22nd, 2017

Project Type Ground up / Warehouse/ NUCOR Metal Building
Project Completion May 2017
Architect Coast Architects
Project Details
Fabrication and Erection of a new 165,000 square foot NUCOR Pre-Engineered Metal Building. Work also included sitework,  finishes, electrical, plumbing, sprinkler, and HVAC systems. Below is a link to the last aerial construction video courtesy of Sky Eye Images.  Mahle Warehouse Jan 2017 Video
Mahle Warehouse, photo courtesy of Sky Eye Images.  www.skyeyeimages.net

Mahle Warehouse

 

 Photo Courtesy of Sky Eye Images. 

 

Reefer Container Yard @ N. Charleston State Ports Authority

Thursday, September 29th, 2016

Project Type Industrial
Project Completion April 2016
Project Details Scope of work included the installation of substations, electrical infrastructure, plug stations, and pipe bollards for the refrigerated container storage at the North Charleston State Ports Authority.

North Charleston State Ports Authority

Marine Terminals – New Shop and Office Buildings

Thursday, January 7th, 2010

Owner Marine Terminal Services
Owners Representative Mr. Joe Jarvis (843) 336-6510
Contract Amount $1,299,264
Completion Date 2006
Project Description Construction of two new metal buildings including:

  • sitework
  • concrete slab and footings
  • an 18,000 sq ft repair shop and 6,600 sq ft office building
    all electrical, plumbing, HVAC, interior partitions, and finishes
Marine Terminal building in progress

Marine Terminal building in progress